Aberystwyth (Private Farm) – diversion of overhead apparatus to clear site for residential development.
Taylor Wimpey – TUSC commenced working with Taylor Wimpey at its East Anton development since 2010. We organised the diversion of an 11kV overhead line, 33kV overhead line and 132kV overhead lines at a fraction of the original overall cost. TUSC liaised with SSE to resolve various issues and expedite the diversions.
Upton Estate – TUSC commenced providing consultancy services to the Estate in 2009, and has assisted with: The diversion of two overhead lines and a voltage regulator; a review of the electricity network across the Estate; the connection of its business park; new connections, new meter installations; a review and organisation of the Estate’s Wayleave Agreements with Western Power Distribution; a review of its telecoms/fibre network; the organisation of a change from a private water supply within the Estate to the installation of a new mains supply adopted by Severn Trent Water.
Kent (Private Estate) – Assistance with mobile operator approach for mast site and associated cables.
Oxfordshire (Private Estate) – Wayleaves and Consents services including agreeing free undergrounding of high voltage electricity overhead line.
Inverloaden and Carrick Estates – Grid Connection works.
Orkney – consents work (negotiation of servitudes) for underground cable as part of Scottish Hydro Electricity Transmission works.